East Elementary School Rebuild

East  logo

Photo of the current East Elementary Building

The Project

  • Construct a new East Elementary on the same property

  • Design and layout similar to North Elementary's two-story building

  • Construction will take place while school is in session minimizing dislpacement of students.

  • Original cost estimate - $31,700,000

East Elementary  Building Rendering

Rendering of the new school

Project Progress

  • Contract Status - 33% complete

  • Contractor - Awarded to Hughes General Contractors

  • Construction bid amount (construction costs only) - $31,562,600

  • Groundbreaking - May 23, 2023

  • Estimated completion date - November 2026

  • Expenditures to date - $12,263,240.11

  • Final Cost - TBD