Canyon View Middle School

Canyon View  Middle School

Canyon View Middle School Cougars

The Project

  • Add three larger performing arts rooms

  • Add two science labs/classrooms

  • Remodel existing science rooms for combined classroom and lab use.

  • Estimated project square footage - 29,000

  • Original estimated cost - $11,360,000

Project Progress

  • Contract Status - 66 percent complete

  • Contractor - Hughes General Contractors

  • Construction Bid Amount (construction costs only) - $13,375,049

  • Construction start date - Feb. 20, 2023

  • Estimated completion - July 2025

  • Construction completed - TBD

Science classrooms need updates

Inadequate space for performing arts