Cedar Middle School

The Project
Add four larger performing arts rooms
Add two science labs/classrooms
Add four general classrooms
Reclaim larger, more adequate room for severe special education needs
Estimated project square footage - 30,455
Original Estimated Cost - $11,700,000
Project Progress
Contract Status - 91% complete.
Contractor - Awarded to Hughes General Contractors
Construction Bid Amount (construction only)- $12,863,261
Expenditures to date - $12,148,262.66
Construction started - July 2022