2021 Bond Logo

Cedar Middle School

Cedar Middle School sign

The Project

  • Add four larger performing arts rooms

  • Add two science labs/classrooms

  • Add four general classrooms

  • Reclaim larger, more adequate room for severe special education needs

  • Estimated project square footage - 30,455

  • Original Estimated Cost - $11,700,000

Project Progress

  • Contract Status - 91% complete.

  • Contractor - Awarded to Hughes General Contractors

  • Construction Bid Amount (construction only)- $12,863,261

  • Expenditures to date - $12,148,262.66

  • Construction started - July 2022

Music directors cut the ribbon to the Cedar Middle School wing

Students look at the music lockers