Cedar High School Science Wing

CHS logo

Cedar High School Building

The Project

  • Remodel the science wing

  • Increase the size of the classrooms

  • Remodel science labs for combined classroom and lab use

  • Original estimated cost - $5,570,000

Project Progress

  • Contract Status - Awarded to Hughes General Contractors

  • Construction Bid Amount - $3,711,184 (Construction only)

  • Final cost, including classroom furniture, equipment - $3,749,315.83

  • Construction started - April 11, 2022

  • Construction completed - January 13, 2023